Leach Highway to Mount Henry Bridge Kwinana Freeway Pedestrian and Cyclist Path

Brentwood, Mount Pleasant

Overview

  • Cycle

    Project type
  • $15.7 million More info

    Total budget
  • Under Construction

    Project phase
  • Main Roads WA

    Lead agency
  • 173

    Jobs supported
  • Early 2021

    Start date

    Late 2021

    End date

This project will complete missing sections of the Kwinana Freeway Principal Shared Path (PSP) between Mount Henry Bridge and Leach Highway, including grade separation at Cranford Avenue.

500 metres of new shared path will be constructed between Leach Highway and Cranford Avenue, with an underpass at Cranford Avenue, as well as 500 meters of upgraded path between Cranford Avenue and Mount Henry Bridge.

The project will improve network connectivity, safety and convenience for people walking and riding.

Benefits

  • Improved shared path facilities alongside Kwinana Freeway
  • Provision of a safe route for people riding and walking in the area
  • New lighting, wayfinding signs, pavement markings and landscaping
  • Completion of final gap in Kwinana Freeway PSP

Project map

This map shows an aerial view of the project location.
Project work area

Detour options

  • Cranford Avenue on-ramp closure

    Significant progress has been made on the new Cranford Avenue underpass, however ongoing inclement weather and the discovery of underground rock has delayed some construction activities.

    This means the Cranford Avenue on-ramp to Kwinana Freeway northbound will remain closed until late November 2021 (subject to change).

    We encourage all road users to follow the signed detour and allow extra time for your journey.