Overview
-
Rail
Project type -
$239 million
Total budget -
Under Construction
Project phase -
METRONET
Lead agency -
TBC
Jobs supported -
Mid 2023
Start date2025
End date
The new Midland Station will replace Midland’s current 53-year-old ageing station and will be relocated between Helena and Cale streets, bringing it closer to the heart of Midland, Midland Health Campus and the Workshops precinct.
The new Midland Station will allow a connection to the new railcar facility in Bellevue and will support safer movements through the area.
The new station will include three longer platforms, bus interchange and more parking, which will greatly improve public transport access to the growing area.
Benefits
Project map
Detour options
-
Works on Yelverton Drive for Cale Street level crossing - 21 March 2024 to late-July 2024
A detour is required to enable Cale Street level crossing works on the southern side of the rail line. Works will be carried out at the intersection of Yelverton Drive and Centennial Place. Traffic will be detoured via Centennial Place and Clayton Street. Access to the hospital from Yelverton Drive will be modified during this period.
-
Partial closure of Railway Parade/Cale Street - 15 Jan 2024 to 24 May 2024
Railway Parade will be closed at the Cale Street intersection and detours will be in place. The closure is to enable the first phase of road works for the new Cale Street level crossing.